Gas safety, EPC and tenancy paperwork in Northern Ireland
Northern Ireland landlords need an annual gas safety check, an EPC when marketing a property, and a Tenancy Information Notice within 28 days of a tenancy starting [1][2][3].
What is the gas safety rule?
Check each appliance and flue at intervals of no more than 12 months and keep the record. Give each existing tenant a copy within 28 days of the check and give new tenants the last record before they move in [1]. These are the rules in force today. SR 2026/178 is a proposed statutory rule (negative resolution) laid on 13 October 2026, whose statutory period ends on 24 November 2026; it is not made [4]. HSENI's consultation on it proposed more flexibility in the timing of a landlord's annual check (regulation 36(3) and a new regulation 36A) [4]. Until it is made, the rules above apply: check with HSENI for changes.
Is an EPC required, and is there a minimum rating?
You need a valid EPC when you market a property for rent. It lasts 10 years and district councils enforce the rule [2]. The penalty charge for a dwelling is £200 [5]. There is no minimum EPC rating for private lets at present; the 2022 Act only gives the Department power to make energy efficiency regulations [6].
What is the Tenancy Information Notice?
A free notice with rent, rights and responsibilities, given within 28 days of the tenancy starting. If the information changes, give a Notice of Variation [3].
Do I need to give receipts?
Landlords or agents must give a written receipt for any cash payment linked to the tenancy. The tenant has a right to receipts for payments made in cash [3].
Worked example: a tenancy starting 1 December 2026
The gas check and EPC were both done on 15 November 2026. The next gas check is due by 14 November 2027, within 12 months [1]. The EPC lasts 10 years and runs to 14 November 2036 [2]. The Tenancy Information Notice, a free notice, is due within 28 days after the tenancy is granted: by 29 December 2026 [3][7].
The new tenant gets the last gas record before moving in; an existing tenant gets a copy within 28 days of each check [1]. The penalty charge for a dwelling under the EPC regulations is £200 [5].
Common mistakes
- Assuming the proposed gas amendment is law. SR 2026/178 is not made and the statutory period ends on 24 November 2026; until it is made, the 12-month rule applies [4].
- Believing a minimum EPC rating applies. None does for private lets at present [6].
- Treating the Tenancy Information Notice as optional. It is due within 28 days [3].
- Not giving receipts for cash payments. A written receipt is required for any cash payment linked to the tenancy [3].
- Letting the gas record lapse because the engineer 'will be round soon'.
What to do next
- Enter the gas, EPC and notice dates in the compliance calendar.
- Recheck HSENI after 24 November 2026 for the outcome of the proposed gas amendment check with HSENI.
- Do the deposit paperwork on the same day: deposits.
- Add the EICR if it is due.
Sources
- Gas Safety (Installation and Use) Regulations (Northern Ireland) 2004, regulation 36
- nidirect: energy performance certificates
- nidirect: private tenancies, landlord and tenant guide
- NI Assembly: Gas Safety (Installation and Use) (Amendment) Regulations (NI) 2026 (SR 2026/178), status
- Energy Performance of Buildings (Certificates and Inspections) Regulations (NI) 2008, regulation 35
- Private Tenancies Act (Northern Ireland) 2022, section 9 (energy efficiency regulations)
- Private Tenancies Act (Northern Ireland) 2022, section 1 (Tenancy Information Notice)
Last checked: . General information, not legal or tax advice. Checked against nidirect, the Department for Communities and legislation.gov.uk. Rules change: always confirm at the source.
Common questions
How often is a gas safety check needed in Northern Ireland?
At intervals of no more than 12 months.
Is there a minimum EPC rating for rentals in Northern Ireland?
No minimum rating applies to private lets at present. An EPC is needed when marketing, with a £200 penalty charge for a dwelling.
Is the proposed gas amendment in force?
No. SR 2026/178 was laid on 13 October 2026 and is not made; the 12-month check applies.
Is a Tenancy Information Notice free?
Yes. It is a free notice given within 28 days of the tenancy starting.
Last updated: . How we source and check pages: editorial policy. Spotted a mistake? Tell us.